The JUBHome BASE load-bearing thermal insulation system for foundation slabs consists of a thermal insulation tub, thermal insulation of the perimeter and the reinforced concrete slab that is poured directly into the thermal insulation tub without any additional bracing. The JUBHome BASE system includes lower and upper layer floor elements as well as edge and corner elements. The latter serve as bracing during concrete pouring. All thermal insulating materials are in accordance with the SIST EN 13163:2013 standard.

blank

  1. FINAL INTERIOR FLOORING
  2. CEMENT SCREED
  3. EUROTHERM STIROTAL SILENT 2,2 + 2,5
  4. REINFORCED CONCRETE FOUNDATION SLAB – thickness up to 30 cm
  5. JUBHome BASE UPPER LAYER FLOOR ELEMENT, d=8, 16 or 22 cm
  6. JUBHome BASE EDGE ELEMENT, d=8 cm
  7. JUBHome LOWER LAYER FLOOR ELEMENT, d=8 cm
  8. HORIZONTAL WATERPROOFING (on top of the blinding concrete) 0,4 cm
  9. CONCRETE BLINDING (beneath this, a layer of compacted fill – hardcore – according to the designer’s specifications)
  1. EUROTHERM EPS F-STRONG-S0
  2. HIDROZOL SUPERFLEX, 0,3 cm
  3. KULIRPLAST or classic finish render (ACRYL/SILICON/SILICON NANO)
  4. STUDDED FOIL (for protection of the waterproofing)
  5. EUROTHERM EPS F-STRONG-S0 8 cm

 

JUBHome BASE assembly

All the elements are fixed either by a grooved or buttoned fit and there is no extra need of gluing. The thermal insulated tub is prepared and cut to size at the factory in accordance to the project plans and everything fits together like “lego” with the supplied assembly plans – fast and simple without problems.  

blank

BASE-BOTTOM

BASE-BOTTOM

BASE-TOP

BASE-TOP

BASE-EDGE

BASE-EDGE

BASE-CORNER_OUT

BASE-CORNER_OUT

BASE-CORNER_IN

BASE-CORNER_IN

 

JUBHome BASE for a variety of construction systems

  1. blankJUBHome WALL

This is a system for the construction of walls out of thermallyinsulating ICF elements made of EPS (ICF – insulated concrete form). The edge elements of the thermal insulation of the JUBHome BASE foundation slab fit directly, without any thermal bridges, into the facade wall which is made of JUBHome WALL wall elements. The ground waterproofing consists of welded bitumen sheets, whereas the vertical waterproofing of the plinth is located directly beneath the render finish.

 

 

  1. blankMASONRY SUPERSTRUCTURES

The exterior plane of the masonry wall is aligned with the face of the JUBHome BASE raft foundation, whereas the thickness of the linear edge element depends on the design thickness of the façade’s thermal insulation. Waterproofing and ground insulation is implemented in the same way as in the case of a JUBHome WALL superstructure.

 

 

 

  1. blankTIMBER FRAME CONSTRUCTION ACCORDING TO A LOW-ENERGY STANDARD

The JUBhome BASE edge elements are geometrically adjusted to the vertical plane of the plinth waterproofing, thus providing a continuous waterproofing barrier when joined to the ground waterproofing layer. In order to ensure less severe waterproofing transitions, the top surface of the edge elements has a lateral. The space between the vertical plinth waterproofing and the facade plane is filled with EUROTHERM EPS F STRONG S0 boards. Vertical waterproofing is either self adhesive or else consists of bituminous waterproofing which is welded onto a base layer of reinforced JUBIZOL adhesive mortar.

 

  1. blankTIMBER FRAME CONSTRUCTION ACCORDING TO A PASSIVE ENERGY STANDARD

The load-bearing structure of the timber frame wall is shifted a certain distance outwards with respect to the vertical edge of the raft foundation. In this case, too, the top surface of the JUBHome BASE edge elements has a lateral slope in order to ensure continuity of the waterproofing and the thermal insulation.

 

 

 

 

 

Penetrations

When designing penetrations through the building exterior we have to ensure proper airtightness, waterproofing and thermal insulation. With a soft thermal insulation layer between the duct and the reinforced concrete slab, a potential horizontal shift in case of a very high horizontal load (eg. big earthquake) is possible.

blank

  1. WATERPROOFING 0,4 cm
  2. ADJUSTABLE BRACE
  3. SOFT THERMAL INSULATION (MINERAL WOOL)
  4. JUBHome BASE LOWER LAYER FLOOR ELEMENT 8 cm
  5. JUBHome BASE UPPER LAYER FLOOR ELEMENT 8, 16 or 22 cm
  6. REINFORCED CONCRETE FOUNDATION SLAB – thickness up to 30 cm

Ground insulation around the perimeter of buildings

In the case of foundations whose bottom edges are located above the expected frost depth, the soil around the perimeters of the thermally insulated foundation slabs has to be thermally insulated. In this way, the occurrence of ice lenses beneath the perimeter can be avoided, including any damage to the waterproofing and the leaching of fine soil particles during freezing / thawing periods. This protection is provided by means of simply-supported EUROTHERM EPS F Strong S0 thermal insulation boards. The latter’s width and thickness depend on the annual average external air temperature at the site.

blank

Source: ARSO