A quick timeline of events in Brestanica – laying down 888 m² of JUBHome BASE foundation insulation.
9:00 – on-site delivery of elements.
10:30 – finished outline and the start of laying down the lower and upper floor elements.
11:30 – …
14:50 – last pallet.
15:00 – finished thermal insulation tub.