A quick timeline of events in Brestanica – laying down 888 m² of JUBHome BASE foundation insulation.

9:00 – on-site delivery of elements.
20170807_090941

10:30 – finished outline and the start of laying down the lower and upper floor elements.
20170807_102959

11:30 – …
20170807_112656

14:50 – last pallet.
20170807_145254

15:00 – finished thermal insulation tub.
20170807_145907